ITP template

An ITP is the document a QA plan is built around: for a given scope of work, every inspection and test it owes, in order, with the hold and witness points marked. Most ITPs live as a spreadsheet or a Word table, filled in by hand as the job goes and quietly diverging from what the spec actually required. The template is not the hard part — turning it into something that gets followed is.

What an ITP has to contain

Every inspection and test the scope of work owes, in the order they happen — receiving through installation, start-up, functional and integrated testing.

The acceptance criteria for each line, not just the activity. "Pressure test" is incomplete; "pressure test, held at X psi for Y minutes, no drop" is an ITP line.

Which lines are hold points (work stops until proven) versus witness points (someone must be present) versus surveillance points (spot-checked, not held) — the three levels most ITP formats distinguish, and conflating them is a common source of dispute.

Who is responsible for each line — contractor, commissioning agent, owner's rep, third-party inspector — and the reference to the specification section it satisfies, so the ITP can be traced back to the contract.

What to look for in software that runs an ITP

  1. 1
    Does the ITP stay a document, or does it become the checklist?
    A tool that stores the ITP as an attachment but runs a separate checklist has two sources of truth that will drift. Look for one where the ITP's lines are the actual steps the work has to pass.
  2. 2
    Are hold, witness and surveillance points distinguished?
    If the tool treats every line the same way, it cannot enforce the difference between "stop and prove it" and "someone should glance at this."
  3. 3
    Can the ITP be written once and reused across units?
    A hand-typed ITP per machine does not scale past a handful of assets. Look for a template tied to the equipment type.
  4. 4
    Does closing a line require the acceptance criteria to actually be met?
    Ask whether a reading outside the stated range can still close the line. If it can, the acceptance criteria are decoration.
  5. 5
    Can the ITP be exported as a signed document if a spec demands it?
    Some specifications still want a bound, signed ITP. If the tool cannot produce that from the live record, you are keeping two systems.

How Veristep does it

The ITP becomes hold-point templates, per discipline

Written once and reused, each line names its evidence type — the acceptance criteria live on the step, not in a separate document nobody re-reads.

Hold points actually hold

A required step will not close without its exact evidence, for the technician, the office, an import or an administrator alike.

Independent acceptance covers the witness-point checks

Where the template calls for a witness, the person who did the work cannot be the one who signs off — set once, enforced every time.

Every asset of a type inherits the same plan

Add a machine of an equipment type and its ITP-derived steps are already there — required, not yet satisfied — from day one.

The plan and the evidence are the same record

There is no separate spreadsheet to keep up to date; the template is the plan, and the check is the evidence that it was followed.

How it fits the way you work

What you bring: your ITP, expressed as hold-point templates that hold the work until it's proven — stricter in practice than a document. If a specification asks for the ITP as a signed, spec-formatted PDF, you produce it from the templates and the export. Surveillance-level sampling plans stay in the tool that runs them; their results come in as evidence. A starting checklist is on the templates page.

Questions people ask

It replaces the enforcement, not necessarily the document. Your ITP becomes hold-point templates per discipline; the template is the plan, the check is the evidence it was followed.

You bring your ITP's content and write it as templates once — Veristep does not currently parse an uploaded ITP document automatically into templates.

Both are expressed as required steps with typed evidence; a witness requirement is enforced through independent acceptance rather than a separate field labelled "witness point."

Yes — a free ITP template, with real hold points, acceptance criteria and sign-off columns across five disciplines, in Excel or CSV. It's on the templates page.

See it refuse to close a step.