A check that will not close

This check cannot close.

Data Center A — the live job.

Anchor & housekeeping pad inspection — ATS-101
ATS-101 · Automatic Transfer Switch 1 · Data Center A — Commissioning
open
0 of 4 required steps hold their evidence
  • Anchor layout per drawingChecklist
  • Anchor torque in specReading in range
  • Pad and anchors photographedPhoto
  • Inspector sign-offSignature
Close this checkcheck cannot close — 4 required step(s) without evidence

That refusal isn’t just a greyed-out button. The office, an import, or an administrator all get the same no. There’s no way around it, and that’s the point.