The tour · 3 of 7Live from a real project. No account needed.
What held
This is why UPS-101 is in the ready column.
Back to Sterling Point — the job that finished.
Cable pull & termination inspection — UPS-101
UPS-101 · Uninterruptible Power Supply 101 · Sterling Point — Data Hall 1 Commissioning
closed
4 of 4 required steps hold their evidence
✓Cable schedule and labeling verifiedpass · captured on siteChecklist
✓Termination torque in spec44.2 ft-lb (in 30-50) · captured on siteReading in range
✓Terminations photographed1 photo · captured on sitePhoto
✓Inspector sign-offErrol Bright · captured on siteSignature
Terminations photographed
Phase conductors landed and labelled, torque stripe on every bolt.
Clearances photographed
Working clearance measured to the demarcation line.
Four different kinds of proof, and each one is a value you could go and check — the torque figure and the band it had to fall inside, the photograph, the name that signed. Every capture carried its coordinates. The case closed because all of it was attached, and the evidence froze at that moment; a correction after this point is added and logged, never written over the top.